You found a 600 square foot plan online, and now the question is whether it fits behind your house. That question comes up on most calls about ADU design and floor plans in Los Angeles, CA. A plan gets drawn once, but it has to sit on one lot with one set of setbacks, one electric panel and one sewer line. And a catalog plan has no idea where your sewer line runs.

California law sets the first two numbers. A city may not require more than a 4-foot side or rear setback, and a new detached ADU of up to 800 square feet is protected (HCD ADU Handbook, March 2026). On a lot 40 feet wide, two 4-foot setbacks leave a 32-foot strip to draw in. Every door and window has to fit inside that strip.

We start with the lot, then the sketch. The survey, the easements, the meter and the sewer line go on one sheet before any room is drawn. After that you get layouts to mark up, and we explain each line on them. The set is written for plan check, so the reviewer finds each answer where they look for it.

ADU Design and Floor Plans in Los Angeles, CA and Nearby Towns

Design calls come from Los Angeles and from Glendale, where rooftop decks on an ADU are off the table, Burbank, which wants 5 feet between a new ADU and the buildings around it, and Pasadena, which hands out free City standard plans.

Signs You Need Plans Drawn to Your Lot

These are the six things people mention first, and each one is a drawing problem.

Printed online plans with notes in the margin on a counter

Plans you found online

A catalog plan knows nothing about your setbacks, easements or sewer line, so it needs redrawing to fit.

A lot survey rolled up with a rubber band on a shelf

Lot survey that is missing

Without a survey the 4-foot setbacks are a guess, and guessed setbacks are what reviewers circle.

A sketch of a studio versus one-bedroom floor plan on graph paper

Studio versus one bedroom

A separate bedroom needs more floor area than a studio, so the choice sets the footprint.

A compact kitchen layout taped out on a plywood floor

Kitchen layout in a small box

In 400 square feet the kitchen and bath often share one plumbing wall, so its position drives the plan.

A back wall with a door facing a neighbor's window across a fence

Door facing a neighbor

An entry pointed at a neighbor's window or fence changes where the door, windows and path go.

An electric meter and a service panel on the side of a stucco house

Meter and panel locations

The new meter and panel need a wall, and in LADWP territory a free meter spot visit comes first.

Plans for Family Living and for a Tenant

The same footprint reads differently to a family member and to a renter.

Plans for family living

A parent or an adult child needs a plan that works every day. That means a level path from the driveway, a doorway wide enough to turn through, a bath without a high tub step and a kitchen window that looks at the yard. We draw those details in at the sketch stage, when moving a wall costs an eraser.

Plan my backyard home

Plans for a tenant

A rental unit lives or dies on its entry. State law says ADUs created under section 66323 can only be rented for terms longer than 30 days (HCD handbook), so the plan is for a long-term neighbor. The door and the meter locations decide how well two households share one lot.

Plan my backyard home
Adu design floor plans at a rental or multi-unit property

How the Design Phase Moves

The design phase has four steps, and the first one happens before anything is drawn.

  1. 01

    Measure the lot

    Survey, setbacks, easements and utilities go on one base sheet before any room is drawn.

  2. 02

    Sketch two layouts

    A studio and a one bedroom get drawn on the same footprint, so the choice is visible.

  3. 03

    Mark it up

    You circle what you would change, and the plan is redrawn until the kitchen, door and windows sit right.

  4. 04

    Finish the plan set

    The set goes out with the engineering and energy sheets, ready for city plan check.

Floor Plans That Work at 400 to 1,200 Square Feet

State law lets an efficiency unit be as small as 150 square feet. It also sets the floor under any city cap: a local limit has to allow at least 850 square feet, or 1,000 if the unit has more than one bedroom. Where a city has no compliant ordinance, the default ceiling for a new detached unit is 1,200 square feet (HCD handbook). So 400 to 1,200 is the working range, and a lot changes between the two ends.

At about 400 square feet you draw one room for sleeping and cooking, plus a bath, and the work is making that room feel bigger than it is. Around 600 a separate bedroom fits, with the kitchen and bath sharing a plumbing wall to keep the pipe runs short. At 800 and up you are drawing two bedrooms, and some cities add a rule: Glendale and Burbank both require a second bedroom once an ADU passes 850 square feet (Glendale ADU page, Burbank ADU handout).

Smaller units cost more per square foot, so halving the footprint does not halve the price.

Stock Plans or Custom Plans?

A ready-made plan is the honest first answer when the lot is simple. Every California city had to run a pre-approved ADU plan program by January 1, 2025 (HCD handbook), and Los Angeles runs its own through the LADBS Standard Plan Program. LADBS says pre-approved plans reduce plan check time. They (the free ones too) still get a final review for site conditions and clearances before a permit issues.

Pasadena offers free City standard plans, with about 3 to 4 weeks of plan check and about 2 weeks for each resubmittal (City of Pasadena). Those plans are meant for lots that are not on a slope, a hillside or expansive soil. Burbank's pre-approved program covers new construction only, so it does nothing for a room conversion (City of Burbank).

Custom plans earn their cost when the lot fights back: a slope, an easement, a tree worth keeping, or a main house with an odd roofline. Ask what changes a program allows before you pay for a plan, because Santa Monica's program permits no modifications at all, and it lists no plans right now (City of Santa Monica).

Odd Lots, Easements and Slopes

Odd lots are where the drawing time goes. Easements, mostly. In Los Angeles, LADWP approval is needed only when the structure sits in or within 10 feet of a Public Utility Easement, and Glendale tells applicants to check with Glendale Water & Power for easement conflicts (LADBS, City of Glendale). We mark every easement on the base sheet first, so the unit gets drawn around it from the first sketch.

Slopes and soil change the drawing too. In mapped landslide or liquefaction zones, cities must require a site-specific geotechnical investigation before permitting most buildings for people to live in (California Geological Survey). Near an active fault a home generally has to stay 50 feet back (Alquist-Priolo rules). A lot like that needs its soils report before the layout is final, because the report can move the footprint.

On a narrow lot the 4-foot setback cap helps a great deal, and the layout comes down to one question: where does the door go, and where does the path to it run?

  • Easements marked on the base sheet
  • Geotechnical report ordered before the layout is final
  • Utility runs traced from the street
  • Door and path planned before the windows
Plan my backyard home
Adu design floor plans: the bigger version of the job

What We Ask of You During Design

Design asks a few things of you, and none of them takes more than an evening.

How long
Design and drawings usually take about one to two months from the first meeting. A ready-made plan can be faster, and a fully custom plan can take longer.
What we ask of you
Your deed or any old survey, photos of the electric meter and panel, and a note on where the sewer cleanout sits. Email them over, and mention any permit paper you have on the house.
Do I need to be home
Once, for the site visit. We agree access to the yard ahead of time, and after that the work is on paper, so a call or an email settles most questions.
Mess and cleanup
Design leaves none. The only fieldwork is a tape measure and a few stakes in the yard, and they come up when we are done.
Permits
We prepare the permit application and answer plan check comments, and you sign the forms the city requires. LADBS takes plans online through ePlanLA and PermitLA (LADBS).
Deposit
Contractors may not take a down payment above the lesser of $1,000 and 10 percent of the price, and a home improvement contract over $500 has to be in writing (Business and Professions Code 7159).

What Moves the Price of ADU Plans

Plans are the smallest piece of an ADU budget. These are planning ranges from published Los Angeles-area figures.

JobFigure
ADU design and floor plans only
A standard plan sits low; custom work, revisions and engineering and energy reports push it up
$7,500 to $25,000
Permit and plan check fees
Government and school fees that the city sets; size, city and hillside or coastal review move them
$5,000 to $20,000
Power, water and sewer connections
Distance to the street, trenching, meter and panel upgrades and sewer location
$3,000 to $20,000
Design plus permit fees together
Our addition of the first two ranges, before any construction
$12,500 to $45,000
Design fees here are the spread found on Los Angeles-area ADU design pages in November 2026. Engineering and reports are priced separately.. Try the cost estimator.

ADU Design Questions, Answered

Can I use an ADU plan I bought online?

Sometimes. A purchased plan is a starting sketch until someone checks it against your setbacks, easements, utility locations and city rules. In Los Angeles even pre-approved plans get a final LADBS review for site conditions and clearances before a permit issues. On a simple lot the redraw is small. On a hard lot the plan needs real changes.

How big can a backyard ADU be in Los Angeles?

California protects a new detached ADU of up to 800 square feet, and any city cap has to allow at least 850 square feet, or 1,000 with more than one bedroom. The City's zoning memo says residential floor area limits in the R1, RE, RS and RA zones cannot block those minimums. Your setbacks may limit the footprint before the size rule does.

Does a new detached ADU need solar panels?

Under the 2025 Energy Code a new detached ADU counts as a new building and needs newly installed solar PV unless an exception applies. An attached ADU is treated as an addition and does not. The panels can be added to the main house's system to meet the rule, so the roof layout goes into the design from the start.

How tall can the roof be on my ADU plan?

A city cannot set a detached ADU height limit below 16 feet. Los Angeles allows 16 feet, or 18 feet within a half mile of major transit, plus 2 feet to match the main roof pitch, which makes 20 in all. Burbank limits detached units to 17 feet to the highest architectural feature. Check the numbers for your address before you fall for a roofline.

What is the smallest ADU I can draw?

State law allows an efficiency unit as small as 150 square feet. That leaves room for a bed, a small bath and a kitchenette, and the layout gets tight fast, since door swings and fixture clearances eat floor area. We lay a 150 and a 600 square foot version over your lot, so you can see what each one gives up.

About us. Eagle Rock Backyard Homes plans backyard homes for owners in Los Angeles and Los Angeles County. Scope and price are agreed in writing before any work starts. More about us.

Get Plans Drawn to Fit Your Lot

Call Eagle Rock Backyard Homes with your address. The written price comes after we see the site.