The cost of an ADU in Los Angeles runs from about $50,000 for a junior unit inside the house to $400,000 for a unit over a garage, and a hillside lot can add more on top. The figures are taken from Los Angeles-area price pages and cost guides we read in November 2026. They tell you which jobs are in the same price class. They do not tell you what your lot will cost.

For scale, the Census Bureau puts the median value of an owner-occupied Los Angeles home at $921,200 (ACS 2020-2024). The estimator below applies the ranges to a type and a size. Past that, the number depends on the slab, the panel, the slope and the city, which is why the price comes in writing after a site visit.

ADU Cost Estimator

Pick a type of ADU and a size. The ranges come from published Los Angeles-area figures and are planning numbers, not a quote.

$180,000 to $300,000
Source: Published Los Angeles-area ADU price pages and cost guides, read November 2026. Your lot, utilities and plans move the real number.

ADU Cost in Los Angeles: The Ranges

Planning figures taken from published sources. A written estimate is the only quote.

Detached ADU Cost in Los Angeles

A new backyard home on its own foundation. Smaller units cost more per square foot, so the price does not fall in step with the size.

JobFigure
Detached ADU, about 600 to 800 sq ft
About $300 to $500 per sq ft at that size; finish level, slope and utility distance move it
$200,000 to $400,000
Detached ADU, 600 sq ft (estimator default)
Worked out as 600 sq ft at $300 to $500 per sq ft
$180,000 to $300,000
The detached adus range above is a planning figure from Los Angeles-area pages read in November 2026. About detached adu construction.

Garage Conversion Cost in Los Angeles

The cheapest way to a legal unit when the garage is sound. The slab and the electrical panel decide most of the spread.

JobFigure
Garage conversion, 350 to 500 sq ft garage
Slab and wall condition, panel upgrade, ceiling height and finish level
$100,000 to $220,000
The garage conversions range above is a planning figure from Los Angeles-area pages read in November 2026. About garage conversion adus.

JADU Cost in Los Angeles

A unit of up to 500 square feet inside the main house.

JobFigure
Junior ADU inside the house, up to 500 sq ft
Kitchen and bath work, a separate entry, and the state of the wiring and plumbing
$50,000 to $150,000
The junior adus range above is a planning figure from Los Angeles-area pages read in November 2026. About junior adu (jadu) conversions.

Attached ADU Cost in Los Angeles

A new unit that shares a wall with the house.

JobFigure
Attached ADU addition, 400 to 800 sq ft
Foundation, how it ties into the house, and finish level
$170,000 to $350,000
The attached adus range above is a planning figure from Los Angeles-area pages read in November 2026. About attached adu additions.

Over-Garage ADU Cost in Los Angeles

A unit built on top of a detached garage. What the garage needs underneath it can change the total.

JobFigure
Second-story ADU over a garage, 400 to 800 sq ft
Footings and posts under the garage, stairs and fire separation
$220,000 to $400,000
The over-garage adus range above is a planning figure from Los Angeles-area pages read in November 2026. About second-story adus over a garage.

Prefab and Modular ADU Cost in Los Angeles

A factory-built unit set on a foundation prepared on site. A unit price alone leaves out delivery, the foundation and hookups.

JobFigure
Prefab or modular ADU, installed, 400 to 800 sq ft
Delivery access and crane, foundation work and utility hookups
$170,000 to $350,000
The prefab and modular range above is a planning figure from Los Angeles-area pages read in November 2026. About prefab and modular adus.

ADU Design Cost in Los Angeles

Drawings for one ADU. Engineering is extra, and a custom design costs more than a standard plan set.

JobFigure
Design and floor plans, one ADU
Standard or custom plan, number of changes, engineering and energy reports
$7,500 to $25,000
The design and plans range above is a planning figure from Los Angeles-area pages read in November 2026. About adu design and floor plans.

ADU Permit and Plan Check Cost in Los Angeles

Government and school fees for one ADU. The city sets these, and faster handling by a third party costs extra.

JobFigure
Permit and plan check fees, one ADU
Size over 500 sq ft, which city, and extra review on hillside or coastal lots
$5,000 to $20,000
Glendale development impact fee on a larger ADU
Glendale says ADUs under 750 sq ft do not pay it
about $5,000
The permits and plan check range above is a planning figure from Los Angeles-area pages read in November 2026 (source). About adu permits and plan check.

In-Law Unit Cost in Los Angeles

An attic, basement or bonus room made into a separate unit.

JobFigure
In-law unit in existing space, about 500 to 800 sq ft
Kitchen and bath work, a separate entry, egress, and the wiring and plumbing already there
$60,000 to $175,000
The in-law units range above is a planning figure from Los Angeles-area pages read in November 2026. About in-law units and existing-space conversions.

ADU Utility Connection Cost in Los Angeles

Power, water and sewer for a second home on the lot.

JobFigure
Utility connections, one ADU on a typical lot
Distance to the street, trenching, meter and panel upgrades, and where the sewer line runs
$3,000 to $20,000
The utility connections range above is a planning figure from Los Angeles-area pages read in November 2026. About adu power, water and sewer connections.

Legalizing an Unpermitted Unit: Cost in Los Angeles

Drawings and permits for a unit built before 2020. Corrections to bring it to code are extra, and they can exceed the permit fees.

JobFigure
Drawings and permits to legalize a unit
This is a thinner estimate than the others; the unit's condition decides the rest
$10,000 to $40,000
The legalizing unpermitted units range above is a planning figure from Los Angeles-area pages read in November 2026. About legalizing an unpermitted adu or garage unit.

Hillside and Tight-Lot Cost in Los Angeles

Slope and access add work to any base build. This row is an add-on, not a total.

JobFigure
Extra cost for a hillside or tight lot
Soils report, deepened footings or caissons, retaining walls, and access for equipment
$30,000 to $90,000
The hillside and tight lots range above is a planning figure from Los Angeles-area pages read in November 2026. About hillside and tight-lot adus.

What Moves ADU Cost in Los Angeles

Size and finish

Smaller units cost more per square foot, because the kitchen, the bath and the utilities cost about the same at any size. Finish level moves the total more than most owners expect.

Slope and access

A narrow side gate or a steep lot means hand carrying, smaller deliveries and more labor. The published hillside add-on runs from $30,000 to $90,000.

Utility distance

The farther the unit sits from the street, the longer the trench for water, sewer and power. Panel and meter upgrades add to it. The published range runs $3,000 to $20,000.

What is under the garage

A conversion depends on the slab and walls already there. A second story depends on whether the garage can carry the load, and footings and posts can change the plan.

City and zone review

Coastal, historic and fire-zone lots can add review steps and reports. Permit and plan check fees run on their own range, $5,000 to $20,000 for government and school fees.

Standard or custom design

A pre-approved plan costs less to draw and can move through plan check faster, though it still gets a final review. A custom design adds drawings and engineering.

How Our Quotes Work

A written price from us lists design and engineering, permit paperwork and construction as separate lines. Permit and plan check fees are shown at cost. Utility connections, landscaping and appliances are each marked as included, as an allowance or as handled by you, so nothing is left unsaid. We write it after the site visit. Planning ranges on this page are for comparing jobs, not for signing.

Cost Questions

How close is the estimator to a real price?

Close enough to plan with, not close enough to sign. The estimator multiplies published Los Angeles-area ranges by a unit type and size, so it cannot see your slab, your panel or your slope. Treat the low end as a tidy lot and the high end as a lot with surprises. A site visit replaces the range with a written number.

Why does a small ADU cost more per square foot?

Because some costs do not shrink with the floor plan. Every ADU needs a kitchen, a bath, a water heater, a panel, a sewer connection and a permit, whether it is 400 square feet or 1,000. Spread over fewer square feet, those fixed costs raise the per-foot figure, which is why the published range for detached units is quoted per foot.

What is not inside these ranges?

Design, permit fees, utility connections and hillside work each have their own row, so a build range may or may not include them. Appliances, landscaping and demolition are the items most often left out or turned into allowances. A written price from us marks each one as included, an allowance or yours. Ask any builder for the same.

What is the most I can be asked to pay up front?

The most a home improvement contractor may take up front is $1,000 or 10 percent of the price, whichever is smaller (Business and Professions Code 7159). Bold type in the contract must state the limit, and later payments follow completed work. A request for a big deposit before any work begins goes beyond the law, so decline it.

Facts We Checked

Want a Real Number for Your Lot?