Garage used for storage only
No cars to rehome, and parking removed by a garage conversion does not have to be replaced under state law.

A garage was built to hold a car, not a household. Find out what the slab, the walls and the panel need before you price the conversion.
Before you price a conversion, the question is if your garage can carry a household: a slab poured for a car, walls with nothing inside the studs, a door wall with no footing under it and a drain line somewhere beneath the floor. Garage conversion ADUs in Los Angeles, CA usually cost less than a new backyard unit: $100,000 to $220,000 as a planning range, where a detached ADU runs $180,000 to $300,000.
If the garage is attached to the house, check one cheaper route first. A junior ADU of up to 500 square feet can use an attached garage as its space, and it has a page of its own. A conversion fits better when you want a full kitchen and bath.
Garage calls come from Glendale, where the city checks easements with its own water and power utility, Long Beach, where conversions are left out of the pre-approved plan program, and Santa Monica, where a converted ADU can reach 850 square feet as a studio or one-bedroom.
These six things about a garage tell us fast whether a conversion is simple or a project.

No cars to rehome, and parking removed by a garage conversion does not have to be replaced under state law.

A slab with wide cracks or a slope toward the door may need a new layer or a moisture barrier on top.

Garage windows are often small and leaky, so each one is kept, replaced or closed up on the plans.

Walls with studs and sheathing only need insulation, wiring and finish before anyone can live behind them.

LADBS asks for a separate electrical panel for a converted unit, so a crowded house panel is only part of it.

The door wall can be rebuilt as an entry wall or a window wall, with a footing the door opening lacked.
Start with the floor. We measure the slab, look for wide cracks, damp patches and a floor drain, and find out which way it slopes. LADBS lets an existing slab stay when it has an approved moisture barrier, and its conversion design assumes new footings 24 inches deep outside and 18 inches deep inside, with four 1/2-inch bars, on soil bearing 1,500 pounds per square foot.
Then the walls and the ceiling. We measure the lowest point of the ceiling, look at the framing and note how far each wall sits from the property line, which the FAQ below ties to fire ratings.
Last the panel and the yard. We look at the main panel, the meter and the wire run to the garage, and we ask for your survey, because Glendale tells applicants to check with Glendale Water & Power that a garage conversion does not sit on an easement.
Assuming the old slab can simply stay. It can stay with an approved moisture barrier, and a slab with a damp patch and a drain beneath it needs a closer look than that.
Planning a bedroom without the escape opening. LADBS wants a converted building to have an egress door 3 feet wide or wider and, in a bedroom, an escape opening of 5.7 square feet or more.
And pricing new doors and windows but not the footing under the old door wall. LA County guidance notes that a garage's front wall usually has no foundation, so new footings have to be added.
A garage unit can house family or a tenant, and the same door and panel rules apply to both.
A converted garage gives a parent, a grown child or a caregiver a private entrance a few steps from your back door. California does not allow a city to require owner-occupancy for an ADU, so you are not tied to living on the property. A garage is one open room, and the egress and escape-opening rules decide where a bedroom can go.
Plan my backyard homeAs a rental, a garage unit has a separate panel and a separate water shut-off, which LADBS requires for a converted unit and which let a tenant's power and water be handled without entering the house. Rentals of an ADU like this must run longer than 30 days under state law, so short stays are out.
Plan my backyard home
A conversion keeps the shell, so the work goes inward, in this order.
Slab, walls, panel, ceiling height and property-line distances get measured and photographed first.
We submit to LADBS or your city and answer corrections; state law gives a city 60 days on a complete application.
The slab gets its fix, the door wall gets a footing, and framing, insulation, panel and plumbing follow.
The city inspects stage by stage, and the final signoff ends with a walk-through of the unit.
Replacement parking worries owners most, and the rules are kinder than they expect. Under state law, parking removed by a garage conversion does not have to be replaced, and Los Angeles requires no parking for an ADU created inside an existing accessory structure.
Slabs are the other hard part. A sound slab can stay with the approved moisture barrier, and a slab with serious cracks may need a new layer poured over it. New footings go under the door wall and anywhere the framing changes how the load reaches the ground.
Low ceilings come last. A low garage ceiling gets fixed only by lowering the floor or raising the roof, and both are big jobs, so we measure first and say so before the plans are drawn.

Typical ADU situations around Los Angeles and the way each tends to unfold.
Example
The garage floor looks fine: a concrete slab, a few hairline cracks, an old floor drain in one corner, one damp patch on a cold morning. The patch and the drain get checked before anyone frames a wall.
First find out how the slab was built. A damp patch can mean no moisture barrier sits under it. Check the thickness at the door opening and trace where the drain line runs. Los Angeles County's notes have the slab verified in the field and a damaged one fixed with a new concrete layer or a vapor barrier, while the City of Los Angeles lets an existing slab stay with an approved moisture barrier. Check which department covers your address.
On a sound slab, the work is a moisture barrier, a built-up floor and new footings at the old door opening. A shallow garage drain gets rerouted before anything is poured, because a kitchen and bath will tie into the sewer instead. County notes for that tie call for it at least 24 inches outside the foundation, a 2 percent slope, cleanouts and a water test.
A badly cracked or sinking slab, a drain that cannot move without breaking the floor, or soil movement goes to an engineer first. Only a field check can say what your slab needs.
What to send: A photo of the whole floor, a close-up of the drain and any damp patch, the inside dimensions and whether the floor slopes toward the door.
A conversion is shorter than a new build, though the paperwork takes as long.
A 350 to 500 square foot garage conversion lands at $100,000 to $220,000 in published Los Angeles-area figures. The slab and wall condition, a panel upgrade, ceiling height and finish level decide where. Check what a quote includes, because design and permits are folded in by some and left out by others.
| Job | Figure |
|---|---|
| Garage conversion ADU, 350 to 500 sq ft Slab and wall condition, panel upgrade, ceiling height, finish | $100,000 to $220,000 |
| Plans for the garage unit A plan set; engineering is priced separately | $7,500 to $25,000 |
| City and school fees Set by the city and the school district | $5,000 to $20,000 |
| Panel, water and sewer work Distance, trenching and where the meter sits | $3,000 to $20,000 |
| Junior ADU in the house, for comparison Up to 500 sq ft inside the main house | $50,000 to $150,000 |
Often not, if you keep it small. A conversion of 750 square feet or under owes no state impact fee, and in Los Angeles ADUs are exempt from park and Affordable Housing Linkage fees. LAUSD school fees begin above 500 square feet, and a larger unit pays impact fees scaled to the main house. Measure the interior floor area first.
Only if the main house has them. State law lets a city require sprinklers in an ADU only when the existing house is sprinklered. Los Angeles adds a second trigger: remodel work alongside the ADU that adds up to more than half of the home's replacement cost inside a year. Ask what the house already has.
A conversion in the existing footprint needs no added setback under state law. LADBS requires a 1-hour fire-rated exterior wall where the conversion wall sits less than 5 feet from the property line, or less than 3 feet if the building is sprinklered.
Yes, often. The HCD handbook lists three formats under section 66323: converting existing space, building a detached ADU and adding a JADU. All three can share one single-family lot. Each unit still has to meet its own rules, and the JADU must sit inside the house, so ask for a combined plan.
A converted unit needs its own electrical panel and its own water shut-off valve that can be reached, says LADBS. Whether it also gets its own utility meter is a question for your utility, and LADWP does a free meter spot visit ahead of a new panel.
About us. Eagle Rock Backyard Homes plans backyard homes for owners in Los Angeles and Los Angeles County. Scope and price are agreed in writing before any work starts. More about us.
Call Eagle Rock Backyard Homes with a photo of the garage floor and panel. The written price comes after a site visit.